title
AGREEMENT BETWEEN THE COUNTY OF DUPAGE, ILLINOIS
AND V3 COMPANIES, LTD
FOR ADDITIONAL PROFESSIONAL ENGINEERING SERVICES
FOR FLOODPROOFING THE COUNTY CAMPUS
FOR FACILITIES MANAGEMENT
(CONTRACT NOT TO EXCEED $394,160.00)
resolution
WHEREAS, the Illinois General Assembly has granted the County of DuPage ("COUNTY") authority to operate, maintain, and keep in repair buildings necessary for County government, and to enter into agreements related to said purpose, pursuant to Illinois Compiled Statutes, Chapter 55, paragraphs 5/5-1106 et. seq.); and
WHEREAS, pursuant to said authority the COUNTY has established a complex of several facilities to provide County governmental services, which complex is commonly referred to as the DuPage County Governmental Campus (“County Campus”); and
WHEREAS, the COUNTY is planning floodproofing improvements to the east and west side of the County campus; and
WHEREAS, V3 COMPANIES, LTD. (hereafter “CONSULTANT”) was originally hired to develop a comprehensive approach and preliminary engineering plans to meet stormwater requirements for the various campus projects, including an assessment of campus stormwater infrastructure, to propose projects, concept options and feasibility, to complete full engineering design and stormwater permitting for the construction of stormwater detention and Best Management Practices (BMP’s) at the County campuses east detention basin, to compile and map historic campus development and detention storage for the campus, and to aid future projects and permitting efforts; and
WHEREAS, the COUNTY requires additional professional engineering services, which includes services, including but not limited to, construction oversight and as-built services, to perform stormwater engineering and coordination for the design, conducting permitting for expected projects on the west side of campus, determining feasibility, design, and permitting for improvements to two (2) stormwater overflow routes., and creating construction drawings to maximize stormwater runoff storage volume and associated best management practices (BMPs) for construction activities at the southwest corner of the County campus; and
WHEREAS, CONSULTANT has experience and expertise in these areas and is in the business of providing such professional engineering services and is willing to perform the required services for an amount not to exceed three hundred ninety-four thousand, one hundred sixty dollars and 00/100 cents ($394,160.00); and
WHEREAS, the County Board has determined that the Stormwater Floodproofing on the east and west sides of the County campus is consistent with the specifications and guidance offered for which American Rescue Plan Act funds can be expended; and
WHEREAS, the COUNTY has selected the CONSULTANT in accordance with the Professional Services Selection Process vetted through a qualification-based selection process in compliance with the Local Government Professional Services Selection Act, 50 ILCS 510/0.01 et. seq.; and
WHEREAS, the Public Works Committee of the DuPage County Board has reviewed and recommended approval of the attached AGREEMENT at the specified amount.
NOW, THEREFORE, BE IT RESOLVED by the DuPage County Board that the attached AGREEMENT between the COUNTY and V3 Companies, Ltd. is hereby accepted and approved in an amount not to exceed three hundred ninety-four thousand, one hundred sixty dollars and 00/100 cents ($394,160.00); and that the Chair of the DuPage County Board is hereby authorized and directed to execute the AGREEMENT on behalf of the COUNTY.
BE IT FURTHER RESOLVED that the DuPage County Clerk be directed to transmit certified copies of this Resolution and the attached AGREEMENT to V3 Companies, Ltd., 7325 Janes Avenue, Woodridge, IL 60517, and to ASA Nicholas Alfonso, Civil Division / DuPage County State’s Attorney’s Office.
end
Enacted and approved this 27th day of August, 2024 at Wheaton, Illinois.
________________________________
DEBORAH A. CONROY, CHAIR
DU PAGE COUNTY BOARD
Attest: ___________________________________
JEAN KACZMAREK, COUNTY CLERK