Legislation Details

File #: 26-1309    Version: 1
Type: Transportation Change Order with Resolution Status: Agenda Ready
File created: 4/22/2026 In control: Transportation Committee
On agenda: 5/5/2026 Final action:
Title: DT-P-0110B-19 AMENDMENT TO RESOLUTION DT-P-0110A-19 ISSUED TO ALFRED BENESCH & COMPANY FOR PROFESSIONAL PHASE II DESIGN ENGINEERING SERVICES CH 27/HIGH LAKE ROAD AT SUNSET AVENUE SECTION 09-00122-03-TL (CONTRACT INCREASE $226,690.03; +100.331%)
Attachments: 1. Alfred Benesch 3874 Change Order, 2. High Lake and Sunset Blair St. Phase II Supplement 2 Scope of Work, 3. High Lake and Sunset Avenue Blair St. Phase II Work Supplement 2 Estimate, 4. BDE 3606 High Lake and Sunset-Supplement 2 Prime&Sub, 5. A Benesch Vendor Ethics, 6. GZA Vendor Ethics
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

title

DT-P-0110B-19

AMENDMENT TO RESOLUTION DT-P-0110A-19

ISSUED TO ALFRED BENESCH & COMPANY

FOR PROFESSIONAL PHASE II DESIGN ENGINEERING SERVICES
CH 27/HIGH LAKE ROAD AT SUNSET AVENUE SECTION 09-00122-03-TL
(CONTRACT INCREASE $226,690.03; +100.331%)

 

resolution

WHEREAS, the DuPage County Board has heretofore approved and adopted Resolutions DT-P-0110A-19 on October 29, 2022, and DT-P-0110-19 on May 14, 2019; and

WHEREAS, a contract was awarded to Alfred Benesch & Company to provide Professional Design (Phase II) Engineering Services for improvements at CH 27/High Lake Road and Sunset Avenue, Section 09-00122-03-TL (hereinafter PROJECT); and

WHEREAS, the current cost of said contract to the County of DuPage, by and through the Division of Transportation, is $225,942.19; and

WHEREAS, the County has secured federal Surface Transportation Program (STP) funding for the roadway portion of the PROJECT, in the amount of $1,333,885.00; and

WHEREAS, after coordination with the Union Pacific Railroad about the proposed improvements, it was determined that a new, enclosed drainage system is necessary along High Lake Road to maintain effective drainage along the roadway and the railroad rights-of-way after the intersection improvements are constructed; and

WHEREAS, through ongoing discussions with the Illinois Commerce Commission, the Winfield Fire Protection District, and the Winfield Township Highway Department, it was determined that the original concept for the intersection improvements would not accommodate the newer emergency vehicles in use by the Fire Protection District and would unnecessarily increase motorists’ delay; and

WHEREAS, proposed changes to the design to include a closed drainage system, revised pavement profiles, geometric improvements, and alternative traffic signal control will provide the best overall improvement for public convenience and safety, and were not included in the current scope of work under Alfred Benesch and Company’s contract; and

WHEREAS, the cost to revise and finalize the plans is $226,690.03; and

WHEREAS, the Transportation Committee recommends a change order to increase the contract in the amount of $226,690.03.

 

 

 

 

 

 

 

 

NOW, THEREFORE, BE IT RESOLVED that the DuPage County Board adopt this Amendment to Resolution DT-P-0110A-19, issued to Alfred Benesch & Company, to increase the funding in the amount of $226,690.03, resulting in an amended contract total amount of $452,632.22, an increase of 100.331%.

end

 

Enacted and approved this 12th day of May, 2026 at Wheaton, Illinois.

 

 

 

________________________________

DEBORAH A. CONROY, CHAIR

DU PAGE COUNTY BOARD

 

 

Attest: ___________________________________

JEAN KACZMAREK, COUNTY CLERK