File #: 25-0478    Version: 1
Type: Change Order Status: Adopted
File created: 2/5/2025 In control: Transportation Committee
On agenda: 2/18/2025 Final action: 2/25/2025
Title: DT-P-0193E-18 AMENDMENT TO RESOLUTION DT-P-0193D-18 ISSUED TO BLA, INC. PROFESSIONAL DESIGN (PHASE II) ENGINEERING SERVICES CH 9/LEMONT ROAD, FROM 83RD STREET TO 87TH STREET SECTION 16-00232-00-CH (CONTRACT INCREASE IN THE AMOUNT OF $54,999.18; +9.89%)
Attachments: 1. BLA Change Order, 2. BLA Decision Memo, 3. Lemont Road - Supplement 5, 4. BLA Exhibit C, 5. Huff and Huff Exhibit C, 6. BLA Vendor Ethics, 7. Huff and Huff Vendor Ethics

title

DT-P-0193E-18

AMENDMENT TO RESOLUTION DT-P-0193D-18
ISSUED TO BLA, INC.
PROFESSIONAL DESIGN (PHASE II) ENGINEERING SERVICES
CH 9/LEMONT ROAD, FROM 83
RD STREET TO 87TH STREET
SECTION 16-00232-00-CH
(CONTRACT INCREASE IN THE AMOUNT OF $54,999.18; +9.89%)

 

resolution

WHEREAS, the DuPage County Board has heretofore approved and adopted Resolutions DT-P-0193-18 on July 17, 2018, DT-P-0193A-18 on August 13, 2019, DT-P-0193B-18 on November 24, 2020, DT-P-0193C-18 on September 14, 2021, and DT-P-0193D-18 on May 9, 2023, which awarded a contract to BLA, Inc., (hereinafter “CONSULTANT”) for Professional Design (Phase II) Engineering Services for improvements along CH 9/Lemont Road, from 83rd Street to 87th Street, Section 16-00232-00-CH (hereinafter “PROJECT”); and

WHEREAS, the current cost of the PROJECT to the County of DuPage, by and through the Division of Transportation, is $558,111.19; and

WHEREAS, due to the ongoing land acquisition process for the PROJECT, it will be necessary to update many of the permits that will expire and/or to update plans, specifications and permits to reflect the latest requirements, standards and special provisions; and

WHEREAS, the Division of Transportation has become aware that additional drainage infrastructure is needed beyond the original project scope; and

WHEREAS, the additional funds are necessary to pay for the incorporation of the additional work into the PROJECT; and

WHEREAS, the Transportation Committee recommends a change order to increase the funding in the amount of $54,999.18; +9.89%. 

NOW, THEREFORE, BE IT RESOLVED that the DuPage County Board adopt this Amendment to Resolution DT-P-0193D-18, issued to BLA, Inc., to increase the funding in the amount of $54,999.18, resulting in an amended contract total amount of $613,110.37; and

 

BE IT FURTHER RESOLVED that the County Clerk transmit a copy of this Resolution and associated Illinois Department of Transportation BLR forms appropriating the necessary motor fuel tax funds to pay for the improvement to the State of Illinois Department of Transportation, by and through the Division of Transportation.

end

 

Enacted and approved this 25th day of February, 2025 at Wheaton, Illinois.

 

 

 