title
RESOLUTION TO APPROVE A SECOND AMENDMENT TO THE 2015 AGREEMENT, BETWEEN THE COUNTY OF DU PAGE AND THE DUPAGE RIVER/SALT CREEK WORKGROUP CONCERNING THE COUNTY’S PARTICIPATION IN DRSCW’S LOCAL FUNDING PROGRAM FOR ALTERNATE STREAM RESTORATION PROJECTS
(TO EXTEND THE TERM OF THE AGREEMENT TO DECEMBER 31, 2030, AND TO INCREASE THE TOTAL CONTRACT PRICE BY $559,697.000; AN INCREASE OF 51%)
resolution
WHEREAS, the DuPage County Board heretofore adopted Resolution PW-R-0271-22, dated July 12, 2022, which approved an Amendment to the 2015 “Financial Commitment in Support for the DuPage River Salt Creek Workgroup Membership Fees” (C.B. Resolution PW-P-0445-15) (hereinafter the “AGREEMENT”) by and between the County of DuPage (hereinafter the “COUNTY”) and the DuPage River/Salt Creek Workgroup (hereinafter the “DRSCW”) for the participation of the COUNTY in a DRSCW local funding program to complete alternate stream restoration projects; and
WHEREAS, the DRSCW Special Condition and the DuPage River Salt Creek Workgroup Implementation Plan, dated April 16, 2015 (hereinafter referred to as “DRSCW Implementation Plan”), further allowed the COUNTY to participate in the DRSCW local funding program to complete alternate stream restoration projects; and
WHEREAS, the current tern of the Amended AGREEMENT is set to expire on or about December 31, 2027, and the current cost of said AGREEMENT was previously approved at $1,096,786; and
WHEREAS, DRSCW has negotiated an extension of the DRSCW Special Condition for an additional 3 years, based on a revision to the DRSCW local funding program; and
WHEREAS, given the DRSCW’s negotiated extension, and after the coordination with DRSCW, the COUNTY and DRSCW now seek to again amend the AGREEMENT to extend the term of the AGREEMENT to December 31, 2030, and for the COUNTY to pay to DRSCW the additional dues & assessments listed in Paragraph 3 of the attached SECOND AMENDMENT; and
WHEREAS, the Public Works Committee recommends that the DuPage County Board approve the attached SECOND AMENDMENT to extend the term of the AGREEMENT until December 31, 2030, and to increase the CONTRACT Price in the amount of $559,697.00; $165,614 to be paid by Stormwater Management, and $394,083 to be paid by Public Works; and
WHEREAS, all other provisions of the AGREEMENT not expressly changed in the attached SECOND AMENDMENT shall remain the same in their entirety.
NOW, THEREFORE, BE IT RESOLVED that the DuPage County Board hereby adopts and approves the attached SECOND AMENDMENT to the 2015 AGREEMENT (C.B. Resolution PW-P-0445-15) previously amended by Resolution PW-R-0271-22, dated July 12, 2022, issued to the DuPage River/Salt Creek Workgroup, to: (i) extend the term of the AGREEMENT until December 31, 2030; and (ii) to increase the CONTRACT price in the amount of $559,697.00; $165,614 to be paid by Stormwater Management, and $394,083 to be paid by Public Works, resulting in an amended contract total amount of $1,656,483, an increase of 51%; and
BE IT FURTHER RESOLVED that one (1) original copy of the SECOND AMENDMENT be transmitted to the DuPage River/Salt Creek Workgroup, by and through the Public Works Department.
end
Enacted and approved 10th day of March, 2026 at Wheaton, Illinois.