Legislation Details

File #: 26-1780    Version: 1
Type: Change Order Status: Agenda Ready
File created: 6/15/2026 In control: Transportation Committee
On agenda: 7/7/2026 Final action:
Title: DT-P-0311A-19 AMENDMENT TO RESOLUTION DT-P-0311-19 ISSUED TO HR GREEN, INC. PROFESSIONAL PRELIMINARY DESIGN ENGINEERING SERVICES SECTION 20-DEENG-03-EG (CONTRACT EXTENSION AND INCREASE OF $100,000.00; +25%)
Attachments: 1. HR Green PO # 4229 Change Order, 2. HR Green Decision Memo, 3. HR Green Vendor Ethics
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

title

DT-P-0311A-19

AMENDMENT TO RESOLUTION DT-P-0311-19
ISSUED TO HR GREEN, INC.
PROFESSIONAL PRELIMINARY DESIGN ENGINEERING SERVICES
SECTION 20-DEENG-03-EG
(CONTRACT EXTENSION AND INCREASE OF $100,000.00; +25%)

 

resolution

WHEREAS, the DuPage County Board heretofore adopted Resolution DT-P-0311-19 on November 12, 2019, which approved a Professional Services Agreement between the County of DuPage (hereinafter “COUNTY”) and HR Green, Inc. for Professional Preliminary Design Engineering Services for various improvements, Section 20-DEENG-03-EG; and

WHEREAS, the current cost of the PROJECT to the County of DuPage, by and through the Division of Transportation, is $400,000.00; and

WHEREAS, the County's proposed culvert replacement on County Highway 5/Park Boulevard requires additional design coordination with the Illinois Department of Transportation’s ongoing project on IL Route 56 (Butterfield Road) to ensure compatibility of the project with the state highway system improvements; and

WHEREAS, the Transportation Committee recommends a change order to increase the contract in the amount of $100,000.00, and to extend the contract completion date through May 31, 2028.

NOW, THEREFORE, BE IT RESOLVED that the DuPage County Board adopt this Amendment to Resolution DT-P-0211-19, issued to HR Green, Inc., to extend the contract completion date to May 31, 2028, and to increase the funding in the amount of $100,000.00, resulting in an amended contract total amount of $500,000.00, an increase of 25%; and

BE IT FURTHER RESOLVED that an original copy of this Resolution and Agreement be transmitted to HR Green, Inc., 2363 Sequoia Drive, Suite 101, Aurora, Illinois 60506, by and through the Division of Transportation.

end

Enacted and approved this 14th day of July, 2026 at Wheaton, Illinois.

 

________________________________

DEBORAH A. CONROY, CHAIR

DU PAGE COUNTY BOARD

 

 

Attest: ___________________________________