title
DT-R-0186B-17
AMENDMENT TO RESOLUTION DT-R-0186A-17
LOCAL PUBLIC AGENCY AGREEMENT
BETWEEN THE COUNTY OF DU PAGE AND THE
ILLINOIS DEPARTMENT OF TRANSPORTATION
FOR IMPROVEMENTS ALONG CH 43/COUNTY FARM ROAD
SECTION 14-00179-31-SP
(DECREASE $91,225.53, -18.93%)
resolution
WHEREAS, the DuPage County Board (hereinafter referred to as COUNTY) has heretofore adopted Resolutions DT-R-0186A-17 on July 17, 2017 and DT-R-0186-17 on March 14, 2017, wherein the County entered into a Local Public Agency Agreement (hereinafter referred to as AGREEMENT) with the Illinois Department of Transportation (hereinafter referred to as STATE) that outlined the financial participation of the parties related to construction for improvements to CH 43/County Farm Road, Section 14-00179-31-SP (hereinafter referred to as IMPROVEMENT); and
WHEREAS, the original cost of said IMPROVEMENT to the County of DuPage, by and through the Division of Transportation, was estimated to be $681,845.00, then amended to be $481,845.00 by DT-R-0186A-17; and
WHEREAS, the IMPROVEMENT has been completed and the COUNTY’s final share is now $390,619.47; and
WHEREAS, an adjustment in funding is in the best interest of the COUNTY and is authorized by law.
NOW, THEREFORE, BE IT RESOLVED, by the DuPage County Board that Resolution DT-R-0186A-17 is hereby amended to reflect a cost of $390,619.47 instead of and in place of $481,845.00, a decrease of $91,225.53,18.93%; an overall decrease of $291,225.53, -42.71%; and
BE IT FURTHER RESOLVED that the County Clerk transmit a copy of this Resolution and the accompanying Illinois Department of Transportation BLR form appropriating the necessary motor fuel tax funds to pay for the actual costs of the IMPROVEMENT to the STATE, by and through the Division of Transportation.
end
Enacted and approved this 13th day of May, 2025 at Wheaton, Illinois.
________________________________
DEBORAH A. CONROY, CHAIR
DU PAGE COUNTY BOARD
Attest: ___________________________________
JEAN KACZMAREK, COUNTY CLERK