File #: 25-1770    Version: 1
Type: Change Order Status: Agenda Ready
File created: 7/22/2025 In control: Transportation Committee
On agenda: 8/5/2025 Final action:
Title: DT-P-0154B-22 AMENDMENT TO RESOLUTION DT-P-0154A-22 AGREEMENT BETWEEN THE COUNTY OF DU PAGE AND KNIGHT E/A, INC. PROFESSIONAL PHASE II DESIGN ENGINEERING SERVICES FOR IMPROVEMENTS ALONG CH 21/FABYAN PARKWAY FROM ILLINOIS ROUTE 38 TO THE COUNTY LINE SECTION 08-00210-03-FP (INCREASE $75,452.66 +9.37%)
Attachments: 1. Knight Change Order, 2. Knight-Decision Memo, 3. Fabyan Amendment 2, 4. Knight Vendor Ethics
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
title
DT-P-0154B-22
AMENDMENT TO RESOLUTION DT-P-0154A-22
AGREEMENT BETWEEN THE COUNTY OF DU PAGE AND KNIGHT E/A, INC.
PROFESSIONAL PHASE II DESIGN ENGINEERING SERVICES
FOR IMPROVEMENTS ALONG CH 21/FABYAN PARKWAY
FROM ILLINOIS ROUTE 38 TO THE COUNTY LINE
SECTION 08-00210-03-FP
(INCREASE $75,452.66 +9.37%)

resolution
WHEREAS, the DuPage County Board heretofore adopted Resolutions DT-P-0154A-22 on August 13, 2024 and DT-P-0154-22 on May 10, 2022, which approved a Local Public Agency Engineering Services Agreement between the County of DuPage and Knight E/A, Inc. (hereinafter referred to as CONSULTANT), to provide Professional Phase II Design Engineering Services for improvements along CH 21/Fabyan Parkway, from Illinois Route 38 to the County Line, Section 08-00210-03-FP; (hereinafter referred to as the AGREEMENT); and
WHEREAS, the current cost of said contract to the County of DuPage, by and through the Division of Transportation is $805,354.66; and
WHEREAS, it has been determined that the existing drainage infrastructure adjacent to Fabyan Parkway cannot meet the current detention requirements for this project; and
WHEREAS, additional engineering work is needed to design a suitable alternative solution addressing the drainage needs for the roadway improvements, which were not included in the original scope of the contract; and
WHEREAS, the Transportation Committee recommends a change order to increase the contract in the amount of $75,452.66 +9.37%, resulting in an amended contract total amount of $880,807.32.
NOW, THEREFORE, BE IT RESOLVED, that the DuPage County Board adopt this Amendment to Resolution DT-P-0154A-22, issued to Knight E/A, Inc., to increase the contract in the amount of $75,452.66 +9.37%, resulting in an amended contract total amount of $880,807.32, a cumulative increase of 20.83%, and









BE IT FURTHER RESOLVED that four (4) origin...

Click here for full text