title
DT-P-0242C-19
AMENDMENT TO RESOLUTION DT-P-0242B-19
ISSUED TO TRANSYSTEMS CORPORATION
PROFESSIONAL PRELIMINARY (PHASE I) ENGINEERING SERVICES
CH 23/NAPERVILLE ROAD AT ILLINOIS 38
INTERSECTION IMPROVEMENTS
SECTION 19-00195-05-CH
(CONTRACT INCREASE $89,844.93, 27.26%)
resolution
WHEREAS, the DuPage County Board has heretofore approved and adopted Resolutions DT-P-0242B-19 on November 8, 2022, DT-P-0242A-19 on March 23, 2021 and DT-P-0242-19 on September 10, 2019; and
WHEREAS, Resolution DT-P-0242-19, awarded a contract to TranSystems Corporation for Professional Phase I Engineering Services for improvements at CH 23/Naperville Road and Illinois 38, Section 19-00195-05-CH; and
WHEREAS, the current cost of said contract to the County of DuPage, by and through the Division of Transportation, is $329,559.09; and
WHEREAS, it has been determined that further unanticipated revisions to the roadway design are necessary to accommodate truck movements, minimize impacts on adjacent properties, and reduce the need for associated land acquisitions; and
WHEREAS, it has also been determined that an additional cultural clearance assessment is required for 17 buildings along Roosevelt Road and Naperville Road that were not included in the original study limit; and
WHEREAS, the cost for these additional tasks was not included in the original contract; and
WHEREAS, the Division of Transportation Committee recommends a change order to increase the contract in the amount of $89,844.93 and an extension through October 31, 2026.
NOW, THEREFORE, BE IT RESOLVED that the DuPage County Board adopt this Amendment to Resolution DT-P-0242B-19, issued to TranSystems Corporation, to increase the funding in the amount of $89,844.93, resulting in an amended contract total amount of $419,404.02, an increase of 15.26% and a cumulative increase of 63.88%.
end
Enacted and approved this 22nd day of October, 2024 at Wheaton, Illinois.
...
Click here for full text