title
DT-R-0313A-21
AMENDMENT TO RESOLUTION DT-R-0313-21
ISSUED TO LORIG CONSTRUCTION
I-355 NOISE ABATEMENT WALL
SECTION 20-NWALL-01-NW
(INCREASE $20,000.00 +5.88%)
resolution
WHEREAS, the DuPage County Board heretofore approved and adopted Resolution DT-R-0313-21 on June 22, 2021; and
WHEREAS, a contract was awarded by County Board Resolution DT-R-0313-21 for the I-355 Noise Abatement Wall, Section 20-NWALL-01-NW; and
WHEREAS, the current cost of said contract to the County of DuPage, by and through the Division of Transportation, is $340,420.50; and
WHEREAS, due to additional grading to ensure positive drainage and restoration, as well as vinyl sleeves for the posts that were not in the original plans, an increase to the contract is recommended; and
WHEREAS, the Division of Transportation Committee recommends a change order to increase the contract in the amount of $20,000.00; and
WHEREAS, an adjustment in funding is in the best interest of the County and authorized by law.
NOW, THEREFORE, BE IT RESOLVED that Resolution DT-R-0313-21, issued to Lorig Construction, is hereby amended to increase the funding in the amount of $20,000.00, resulting in an amended contract total amount of $360,420.50, an increase of 5.88%.
end
Enacted and approved this 11th day of April, 2023 at Wheaton, Illinois.
________________________________
DEBORAH A. CONROY, CHAIR
DU PAGE COUNTY BOARD
Attest: ___________________________________
JEAN KACZMAREK, COUNTY CLERK