Dupage Logo
To view previous Board or Committee Meetings, please visit our YouTube channel.
Those wishing to submit virtual public comments, please use the Public Comment Form.
File #: 25-0654    Version: 1
Type: Budget Transfer Status: Agenda Ready
File created: 2/24/2025 In control: Public Works Committee
On agenda: 3/4/2025 Final action: 3/4/2025
Title: Public Works - $775,000 budget transfer needed due to sewer lining projects that carried over from Fiscal Year 2024. These were originally budgeted under Sewer Treatment Plant Construction during capital planning and does not change the overall Capital Budget for Public Works. Funds will move from account 2000-2555-54030 (Sewer & Water Treatment Plant Construction) in the amount of $775,000, to account 2000-2555-54070 (Waste Water System Infrastructure).
Attachments: 1. Public Works Budget Transfer_Redacted