File #: 25-1009    Version: 1
Type: Change Order Status: Sent to Finance
File created: 4/7/2025 In control: Transportation Committee
On agenda: 4/15/2025 Final action:
Title: DT-R-0061A-23 AMENDMENT TO RESOLUTION DT-R-0061-23 TO R.W. DUNTEMAN COMPANY. 2023 PAVEMENT MAINTENANCE (NORTH) PROGRAM SECTION 23-PVMTC-19-GM (INCREASE $150,610.95, + 2.39%)
Attachments: 1. RW Dunteman Requisition 6406, 2. R.W. Dunteman 23-PVMTC-19-GM Supporting Data
title
DT-R-0061A-23
AMENDMENT TO RESOLUTION DT-R-0061-23
TO R.W. DUNTEMAN COMPANY.
2023 PAVEMENT MAINTENANCE (NORTH) PROGRAM
SECTION 23-PVMTC-19-GM
(INCREASE $150,610.95, + 2.39%)

resolution
WHEREAS, the DuPage County Board heretofore adopted Resolution DT-R-0061-23 on April 25, 2023; and
WHEREAS, a contract was awarded by County Board Resolution DT-R-0061-23 to R.W. Dunteman Company for the 2023 Pavement Maintenance (North) Program, Section 23-PVMTC-19-GM; and
WHEREAS, changes to the contract plans, pay items and/or contract quantities were necessary due to field conditions, as listed on the attached "Supporting Data for Amendment"; and
WHEREAS, in order to construct sidewalks in accordance with the Americans with Disabilities Act it was necessary to extend the original limits of sidewalk removal and replacement; and
WHEREAS, to match existing field conditions and provide a satisfactory final pavement, the limits of paving were adjusted; and
WHEREAS, unforeseeable deteriorated curb and gutter was discovered at a later stage of the project after the existing pavement surface was removed and additional removal and replacement was required to provide a structurally sound roadway; and
WHEREAS, in response to a request from a local Village regarding a specific location requiring supplemental grading and sidewalk modifications to ensure adequate access for all road users, it was determined to be in the best interest of the County to add the work to regrade and reconstruct the sidewalk to this contract; and
WHEREAS, the plan resurfacing limit did not allow for an existing drainage issue to be corrected requiring the limit to be extended and the area regraded and repaved; and
WHEREAS, an adjustment in funding is in the best interest of the County and is authorized by law.