AWARDING RESOLUTION
ISSUED TO COPENHAVER CONSTRUCTION INC.,
FOR THE ST. JOSEPH CREEK CONDOMINIUM DRAINAGE IMPROVEMENTS -
BUILDINGS A&B
(CONTRACT AMOUNT $2,035,871)
resolution
WHEREAS, bids have been taken and processed in accordance with County Board policy;
WHEREAS, the lowest most responsible bidder has been designated and the Stormwater Management Committee recommends County Board approval for the issuance of a contract for the St. Joseph Creek Condominium Drainage Improvements - Buildings A&B.
NOW, THEREFORE, BE IT RESOLVED that County Contract, covering said, for the St. Joseph Creek Condominium Drainage Improvements - Buildings A&B, for the Stormwater Management Department, be and it is hereby approved for issuance of a Contract by the Procurement Division, to Copenhaver Construction, Inc., 75 Koppie Dr., Gilberts, IL 60136, for the total contract amount not to exceed $2,035,871, per lowest responsible Bid # 24-084-SWM.
end
Enacted and approved this 13th day of August, 2024 at Wheaton, Illinois.
________________________________
DEBORAH A. CONROY, CHAIR
DU PAGE COUNTY BOARD
Attest: ___________________________________
JEAN KACZMAREK, COUNTY CLERK