File #: 25-2299    Version: 2
Type: Change Order Status: Sent to Finance
File created: 9/19/2025 In control: Stormwater Management Committee
On agenda: 10/7/2025 Final action:
Title: SM-P-0021A-24 AMENDMENT TO RESOLUTION SM-P-0021-24 ISSUED TO COPENHAVER CONTRUCTION, INC. FOR THE ST. JOSEPH CREEK CONDOMINIUM DRAINAGE IMPROVEMENTS - BUILDING C (CONTRACT INCREASE $59,300)
Attachments: 1. Change Order 1 - Copenhaver, 2. Decision Memo CO#1 - Copenhaver, 3. Vendor Ethics - Copenhaver - Redacted

title
SM-P-0021A-24

AMENDMENT TO RESOLUTION SM-P-0021-24
ISSUED TO COPENHAVER CONTRUCTION, INC. FOR THE
ST. JOSEPH CREEK CONDOMINIUM DRAINAGE IMPROVEMENTS - BUILDING C

(CONTRACT INCREASE $59,300)

 

resolution

 

WHEREAS, Resolution SM-P-0021-24 was approved and adopted by the County Board on August 13th, 2024; and

 

WHEREAS, the Stormwater Management Committee recommends changes as stated in the change order to Copenhaver Construction, Inc., for the St. Joseph Creek Condominium Drainage Improvements Project - Building C, for Stormwater Management.

 

NOW, THEREFORE, BE IT RESOLVED, the County Board adopts the Change Order to the contract issued to Copenhaver Construction, Inc., for the St. Joseph Creek Condominium Drainage Improvements - Building C, for Stormwater Management, to increase the contract in the amount of $59,300, taking the contract amount of $1,720,415, resulting in an amended contract total not to exceed $1,779,715. 

 

end

Enacted and approved this 14th day of October, 2025 at Wheaton, Illinois.

 

 

 

________________________________

 

DEBORAH A. CONROY, CHAIR

DU PAGE COUNTY BOARD

 

 

 

Attest: ___________________________________

 

JEAN KACZMAREK, COUNTY CLERK