File #: 24-2017    Version: 1
Type: Change Order Status: Adopted
File created: 7/22/2024 In control: Transportation Committee
On agenda: 8/6/2024 Final action: 8/13/2024
Title: DT-P-0154A-22 AMENDMENT TO RESOLUTION DT-P-0154-22 AGREEMENT BETWEEN THE COUNTY OF DU PAGE AND KNIGHT E/A, INC. PROFESSIONAL PHASE II DESIGN ENGINEERING SERVICES FOR IMPROVEMENTS ALONG CH 21/FABYAN PARKWAY FROM ILLINOIS ROUTE 38 TO THE COUNTY LINE SECTION 08-00210-03-FP (INCREASE $76,405.80 +10.48%)
Attachments: 1. Knight Change Order, 2. Knight Decision Memo, 3. Knight Fabyan Amendment 1, 4. Knight Vendor Ethics
title
DT-P-0154A-22
AMENDMENT TO RESOLUTION DT-P-0154-22
AGREEMENT BETWEEN THE COUNTY OF DU PAGE AND KNIGHT E/A, INC.
PROFESSIONAL PHASE II DESIGN ENGINEERING SERVICES
FOR IMPROVEMENTS ALONG CH 21/FABYAN PARKWAY
FROM ILLINOIS ROUTE 38 TO THE COUNTY LINE
SECTION 08-00210-03-FP
(INCREASE $76,405.80 +10.48%)

resolution
WHEREAS, the DuPage County Board heretofore adopted Resolution DT-P-0154-22 on May 10, 2022, which approved a Local Public Agency Engineering Services Agreement between the County of DuPage and Knight E/A, Inc. (hereinafter referred to as CONSULTANT), to provide Professional Phase II Design Engineering Services for improvements along CH21/ Fabyan Parkway, from Illinois Route 38 to the County Line, Section 08-00210-03-FP; (hereinafter referred to as the AGREEMENT); and
WHEREAS, the current cost of said contract to the County of DuPage, by and through the Division of Transportation is $728,648.86; and
WHEREAS, it has been determined during the environmental coordination of the project, that IDOT instituted work restrictions on part of the project site due to proximity to a detention pond used by a threatened and endangered common gallinule. This restriction requires major changes to the maintenance of traffic plans, which was not expected; and
WHEREAS, during the land acquisition process, the property owner requested impacts to their business sign and retaining walls be avoided. This work requires a redesign of the proposed curb line and storm sewer and changes to the proposed plans. All of this work is not included in the original scope of the contract; and
WHEREAS, the Transportation Committee recommends a change order to increase the contract in the amount of $76,405.80 resulting in an amended contract total amount of $805,354.66.
NOW, THEREFORE, BE IT RESOLVED, that the DuPage County Board adopt this Amendment to Resolution DT-P-0154-22, issued to Knight E/A, Inc., to in...

Click here for full text