title
DT-R-0030A-24
AMENDMENT TO RESOLUTION DT-R-0030-24
TO ALLIANCE CONTRACTORS, INC.
2024 RETAINING WALL REPAIR PROGRAM
SECTION 23-RETWL-04-MS
(INCREASE $104,312.20, + 29.4%)
resolution
WHEREAS, the DuPage County Board heretofore adopted Resolution DT-R-0030-24 on August 13, 2024; and
WHEREAS, a contract was awarded by County Board Resolution DT-R-0030-24 to Alliance Contractors, Inc. for the 2024 Retaining Wall Repair Program, Section 23-RETWL-04-MS; and
WHEREAS, changes to the contract plans, pay items and/or contract quantities were necessary due to field conditions, as listed on the attached "Supporting Data for Amendment"; and
WHEREAS, to satisfy a previous agreement with an adjacent property owner it was necessary to add additional landscape material at one project location; and
WHEREAS, in order to comply with the Railroads safety regulations and access requirements for working adjacent to their property it was necessary for Alliance Contractors, Inc. to obtain a Railroad Permit and additional insurance; and
WHEREAS, an additional project location was included in the program budget, designed, and included in the original contract plans, but was eliminated prior to bidding due to Right-of-Way acquisition being incomplete; and
WHEREAS, during the course of the contract the Right-of-Way was acquired, and as the Contractor has agreed to extend the contract bid prices to the additional project location the Division of Transportation has determined it is in the best interest of the County to add the additional project location to the existing contract; and
WHEREAS, an adjustment in funding is in the best interest of the County and is authorized by law.
NOW, THEREFORE, BE IT RESOLVED that the DuPage County Board adopt this Amendment to Resolution DT-R-0030-24, issued to Alliance Contractors, Inc., to increase the funding in the amount...