File #: 25-2171    Version: 1
Type: Change Order Status: Agenda Ready
File created: 9/4/2025 In control: Transportation Committee
On agenda: 9/16/2025 Final action:
Title: DT-P-0001A-24 AMENDMENT TO RESOLUTION DT-P-0001-24 AGREEMENT BETWEEN THE COUNTY OF DU PAGE AND CIORBA GROUP, INC. PROFESSIONAL PHASE II DESIGN ENGINEERING SERVICES CH 11/ARMY TRAIL ROAD BRIDGE OVER WEST BRANCH DUPAGE RIVER SECTION 21-00240-09-BR (CONTRACT INCREASE $49,885.00; +7.55%)
Attachments: 1. Ciorba Change Order, 2. Ciorba Decision Memo, 3. Ciorba Supplement, 4. Ciorba Vendor Ethics
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
title
DT-P-0001A-24
AMENDMENT TO RESOLUTION DT-P-0001-24
AGREEMENT BETWEEN THE COUNTY OF DU PAGE
AND CIORBA GROUP, INC.
PROFESSIONAL PHASE II DESIGN ENGINEERING SERVICES
CH 11/ARMY TRAIL ROAD BRIDGE OVER WEST BRANCH DUPAGE RIVER
SECTION 21-00240-09-BR
(CONTRACT INCREASE $49,885.00; +7.55%)

resolution
WHEREAS, the DuPage County Board heretofore adopted Resolution DT-P-0001-24 on December 12, 2024 approving a Professional Services Agreement between the County of DuPage (hereinafter "COUNTY") and Ciorba Group which requires Professional Phase II Design Engineering Services for improvements along CH 11/Army Trail Road bridge over West Branch DuPage River, Section 21-00240-09-BR (hereinafter "PROJECT"); and
WHEREAS, the current cost of the PROJECT to the COUNTY, by and through the Division of Transportation, is $660,323.04; and
WHEREAS, during the development of the Phase II plans, it was determined that due to the project's proximity to the Gerber Road intersection, pedestrian access improvements at the intersection are necessary. Additional unanticipated work includes additional land acquisition coordination and determination due to utility relocation, as well as related changes to the plans, specifications, estimates, and stormwater permit to be updated by Ciorba Group, Inc.; and
WHEREAS, increased funding is necessary to pay for the additional unanticipated work on the PROJECT; and
WHEREAS, the Transportation Committee recommends approval of a change order to increase the funding in the amount of $49,885.00 to cover these costs.











NOW, THEREFORE, BE IT RESOLVED that Resolution DT-P-0001-24 is amended to reflect a cost of $710,208.04 instead of and in place of a cost of $660,323.04, an increase of 7.55%.
end

Enacted and approved this 23rd day of September, 2025 at Wheaton, Illinois.