File #: 25-0478    Version: 1
Type: Change Order Status: Adopted
File created: 2/5/2025 In control: Transportation Committee
On agenda: 2/18/2025 Final action: 2/25/2025
Title: DT-P-0193E-18 AMENDMENT TO RESOLUTION DT-P-0193D-18 ISSUED TO BLA, INC. PROFESSIONAL DESIGN (PHASE II) ENGINEERING SERVICES CH 9/LEMONT ROAD, FROM 83RD STREET TO 87TH STREET SECTION 16-00232-00-CH (CONTRACT INCREASE IN THE AMOUNT OF $54,999.18; +9.89%)
Attachments: 1. BLA Change Order, 2. BLA Decision Memo, 3. Lemont Road - Supplement 5, 4. BLA Exhibit C, 5. Huff and Huff Exhibit C, 6. BLA Vendor Ethics, 7. Huff and Huff Vendor Ethics
title
DT-P-0193E-18
AMENDMENT TO RESOLUTION DT-P-0193D-18
ISSUED TO BLA, INC.
PROFESSIONAL DESIGN (PHASE II) ENGINEERING SERVICES
CH 9/LEMONT ROAD, FROM 83RD STREET TO 87TH STREET
SECTION 16-00232-00-CH
(CONTRACT INCREASE IN THE AMOUNT OF $54,999.18; +9.89%)

resolution
WHEREAS, the DuPage County Board has heretofore approved and adopted Resolutions DT-P-0193-18 on July 17, 2018, DT-P-0193A-18 on August 13, 2019, DT-P-0193B-18 on November 24, 2020, DT-P-0193C-18 on September 14, 2021, and DT-P-0193D-18 on May 9, 2023, which awarded a contract to BLA, Inc., (hereinafter "CONSULTANT") for Professional Design (Phase II) Engineering Services for improvements along CH 9/Lemont Road, from 83rd Street to 87th Street, Section 16-00232-00-CH (hereinafter "PROJECT"); and
WHEREAS, the current cost of the PROJECT to the County of DuPage, by and through the Division of Transportation, is $558,111.19; and
WHEREAS, due to the ongoing land acquisition process for the PROJECT, it will be necessary to update many of the permits that will expire and/or to update plans, specifications and permits to reflect the latest requirements, standards and special provisions; and
WHEREAS, the Division of Transportation has become aware that additional drainage infrastructure is needed beyond the original project scope; and
WHEREAS, the additional funds are necessary to pay for the incorporation of the additional work into the PROJECT; and
WHEREAS, the Transportation Committee recommends a change order to increase the funding in the amount of $54,999.18; +9.89%.
NOW, THEREFORE, BE IT RESOLVED that the DuPage County Board adopt this Amendment to Resolution DT-P-0193D-18, issued to BLA, Inc., to increase the funding in the amount of $54,999.18, resulting in an amended contract total amount of $613,110.37; and

BE IT FURTHER RESOLVED that the County Clerk transmit a copy of this Resolution and associated Illinois Department of Transportation BLR f...

Click here for full text