File #: 25-0842    Version: 1
Type: Change Order Status: Sent to Finance
File created: 3/24/2025 In control: Transportation Committee
On agenda: 4/15/2025 Final action:
Title: DT-P-0062A-21 AMENDMENT TO RESOLUTION DT-P-0062-21 ISSUED TO ATLAS ENGINEERING GROUP, LTD PROFESSIONAL CONSTRUCTION ENGINEERING SERVICES SECTION 21-CENGR-08-EG (DECREASE $72,542.50 AND CLOSE; -18.14%)
Attachments: 1. Atlas Engineering 5177 Change Order Requisition

title

DT-P-0062A-21

AMENDMENT TO RESOLUTION DT-P-0062-21
ISSUED TO ATLAS ENGINEERING GROUP, LTD

PROFESSIONAL CONSTRUCTION ENGINEERING SERVICES
SECTION 21-CENGR-08-EG
(DECREASE $72,542.50 AND CLOSE; -18.14%)

 

resolution

WHEREAS, the DuPage County Board heretofore adopted Resolution DT- P-0062-21 on March 23, 2021; and

WHEREAS, a contract was awarded by County Board Resolution DT- P-0062-21 to Atlas Engineering Group, LTD for Professional Construction Engineering Services, Section 21- CENGR-08-EG; and

WHEREAS, the current contract total amount is $400,000.00; and

WHEREAS, Atlas Engineering Group, Inc. has completed all obligations under the contract, and there are allocated and unexpended funds remaining under the contract; and

WHEREAS, it is in the best interest of the County to de-obligate the remaining funds and close out the contract, and said change is authorized by law.

NOW, THEREFORE, BE IT RESOLVED that the DuPage County Board hereby decreases the funding in the amount of $72,542.50, and close the contract, resulting in a final County cost of $327,457.50, a decrease of 18.14%.

end

 

Enacted and approved this 22nd day of April, 2025 at Wheaton, Illinois.

 

 

 

________________________________

DEBORAH A. CONROY, CHAIR

DU PAGE COUNTY BOARD

 

 

Attest: ___________________________________

JEAN KACZMAREK, COUNTY CLERK