File #: DT-R-0023-24    Version: 1
Type: Transportation Resolution Status: Adopted
File created: 5/15/2024 In control: Transportation Committee
On agenda: 5/21/2024 Final action: 5/28/2024
Title: LETTER OF UNDERSTANDING BETWEEN THE COUNTY OF DU PAGE AND THE ILLINOIS DEPARTMENT OF TRANSPORTATION (IDOT) 31ST STREET AT NORTH AND SOUTH RAMPS (IL ROUTE 83) MAINTENANCE RESPONSIBILITIES FOR DUPAGE EQUIPMENT ON IDOT SIGNALS (100% COUNTY COST ON FUTURE MAINTENANCE, 15% COUNTY COST ON FUTURE ENGINEERING)
Attachments: 1. LOU-31st at NS ramps
title
LETTER OF UNDERSTANDING
BETWEEN THE COUNTY OF DU PAGE AND
THE ILLINOIS DEPARTMENT OF TRANSPORTATION (IDOT)
31ST STREET AT NORTH AND SOUTH RAMPS (IL ROUTE 83)
MAINTENANCE RESPONSIBILITIES FOR DUPAGE EQUIPMENT ON IDOT SIGNALS
(100% COUNTY COST ON FUTURE MAINTENANCE,
15% COUNTY COST ON FUTURE ENGINEERING)

resolution
WHEREAS, the DuPage County (hereinafter "COUNTY"), has improved the existing 31st Street, providing widening and resurfacing from Meyers Road to York Road in addition to traffic signal improvements (hereinafter "PROJECT"); and

WHEREAS, the ILLINOIS DEPARTMENT OF TRANSPORTATION (hereinafter "IDOT") and COUNTY, are parties to an Intergovernmental Agreement [BR1][SZ2]that documents their respective responsibilities for design, construction, utility relocation, costs, right of way, maintenance and jurisdiction over the PROJECT work within the County limits; and

WHEREAS, as part of PROJECT, COUNTY has performed improvements along certain traffic signals whose maintenance and jurisdiction is with IDOT, improvements including installation of emergency vehicle pre-emption systems (hereinafter "EVP") and LED Illuminated Street name signs (hereinafter "ILLUMINATED SIGNS"), specifically at 31st Street and South Ramp to IL Route 83 and 31st Street and North Ramp to IL Route 83; and

WHEREAS, based on IDOT policy, any costs and maintenance responsibilities for EVP or ILLUMINATED SIGNS are to be assumed by an outside entity for such devices to be permitted to remain installed and in operation at any traffic signal under the jurisdiction of IDOT; and

WHEREAS, a Letter of Understanding dated March 6, 2024, has been prepared and is attached hereto. Said Letter of Understanding outlines the scope of the PROJECT as well as the rights, and responsibilities of the COUNTY and IDOT for the concurrence of installation, maintenance, and related financial responsibilities of the PROJECT EVP and ILLUMINATED SIGNS; and

...