title
DT-P-0192A-19
AMENDMENT TO RESOLUTION DT-P-0192-19
ISSUED TO FARNSWORTH GROUP, INC. FOR
PROFESSIONAL TRAFFIC SIGNAL DESIGN ENGINEERING SERVICES
SECTION 19-TSENG-02-EG
(DECREASE $64,524.32 AND CLOSE; -16.13%)
resolution
WHEREAS, the DuPage County Board heretofore adopted Resolution DT-P-0192-19 on July 16th, 2019, to award a contract to Farnsworth Group, Inc. for professional traffic signal design engineering services for various locations, Section 19-TSENG-02-EG; and
WHEREAS, the current contract total amount is $400,000.00; and
WHEREAS, Farnsworth Group, Inc. has completed all obligations under the contract, and there are allocated and unexpected funds remaining under the contract; and
WHEREAS, it is in the best interest of the County to de-obligate the remaining funds and close out the project, and said change is authorized by law.
NOW, THEREFORE, BE IT RESOLVED that the DuPage County Board hereby decreases the funding in the amount of $64,524.32, resulting in a final County cost of $335,475.68, a decrease of 16.13%.
end
Enacted and approved this 25th day of February, 2025 at Wheaton, Illinois.
________________________________
DEBORAH A. CONROY, CHAIR
DU PAGE COUNTY BOARD
Attest: ___________________________________
JEAN KACZMAREK, COUNTY CLERK