AWARDING RESOLUTION ISSUED TO
HOERR CONSTRUCTION
FOR MANHOLE REHABILITATION IN 31 MANHOLES AROUND DUPAGE COUNTY
FOR PUBLIC WORKS
(CONTRACT TOTAL AMOUNT $118,726.66)
resolution
WHEREAS, the County of DuPage by virtue of its power set forth in the Counties Code (55 ILCS 5/1-1001 et seq.) is authorized to enter into this Agreement; and
WHEREAS, pursuant to the Governmental Joint Purchasing Act (30 ILCS 525/2), the County is authorized to enter into a Joint Purchasing Agreement for manhole rehabilitation in 31 manholes around DuPage County; and
WHEREAS, pursuant to Intergovernmental Agreement between the County of DuPage and the Omnia Partners Cooperative Agreement, the County of DuPage will contract with Hoerr Construction; and
WHEREAS, the Public Works Committee recommends County Board approval for the issuance of a contract to Hoerr Construction, for manhole rehabilitation in 31 manholes around DuPage County, for the period of March 10, 2026 through November 30, 2026, for Public Works.
NOW, THEREFORE BE IT RESOLVED, that County contract, covering said for manhole rehabilitation in 31 manholes around DuPage County, for the period of March 10, 2026 through November 30, 2026, for Public Works, be, and it is hereby approved for issuance of a contract by the Procurement Division to Hoerr Construction, 1416 County Road 200 N P.O. Box 65, Goodfield, Illinois, 61742, for a contract total amount not to exceed $118,726.66, per contract pursuant to the Omnia Partners Cooperative Agreement #23-065-PW.
end
Enacted and approved on this 10th day of March, 2026 at Wheaton, Illinois.
________________________________
DEBORAH A. CONROY, CHAIR
DU PAGE COUNTY BOARD
Attest: ___________________________________
JEAN KACZMAREK, COUNTY CLERK