File #: 24-2003    Version: 1
Type: Change Order Status: Adopted
File created: 7/17/2024 In control: Stormwater Management Committee
On agenda: 8/6/2024 Final action: 8/13/2024
Title: SM-P-0059A-23 AMENDMENT TO RESOLUTION SM-P-0053-23 ISSUED TO HEY & ASSOCIATES, INC., FOR PROFESSIONAL ENGINEERING SERVICES TO DESIGN STREAMBANK STABILIZATION PROJECTS THROUGHOUT THE COUNTY ( CONTRACT INCREASE $48,205)
Attachments: 1. Change Order- Hey, 2. Decision Memo - Hey, 3. Vendor Ethics - Hey

 

title

SM-P-0059A-23

AMENDMENT TO RESOLUTION SM-P-0053-23 ISSUED TO HEY & ASSOCIATES, INC., FOR PROFESSIONAL ENGINEERING SERVICES TO DESIGN STREAMBANK STABILIZATION PROJECTS THROUGHOUT THE COUNTY

( CONTRACT INCREASE $48,205)

resolution

 

 

WHEREAS, Resolution SM-P-0059-23, was approved and adopted by the County Board on July 11, 2023; and

 

WHEREAS, the Stormwater Management Committee recommends changes as stated in the change order to Hey & Associates, Inc., for Professional Engineering Services to design streambank stabilization projects throughout the County, for Stormwater Management.

 

NOW, THEREFORE, BE IT RESOLVED, the County Board adopts the Change Order, dated July 16, 2024 to the contract issued to Hey & Associates, Inc., for Professional Engineering Services to design streambank stabilization projects throughout the County, for Stormwater Management, to increase the contract in the amount of $48,205, taking the contract amount of $85,000, resulting in an amended contract total not to exceed $133,205, an increase of 56.71%. 

 

end

Enacted and approved this 13th day of August, 2024 at Wheaton, Illinois.

 

 

 

________________________________

 

DEBORAH A. CONROY, CHAIR