File #: 25-2168    Version: 1
Type: Change Order Status: Agenda Ready
File created: 9/4/2025 In control: Transportation Committee
On agenda: 9/16/2025 Final action:
Title: DT-P-0003A-24 AMENDMENT TO RESOLUTION DT-P-0003-24 ISSUED TO ALFRED BENESCH & COMPANY PROFESSIONAL CONSTRUCTION ENGINEERING SERVICES GENEVA ROAD BRIDGE OVER THE WEST BRANCH DUPAGE RIVER SECTION 18-00206-10-BR (CONTRACT INCREASE $138,568.00; +16.12%)
Attachments: 1. A Benesch Change Order, 2. A Benesch Decision Memo, 3. A Benesch Exhibit C-revised, 4. A Benesch Supplement #1, 5. A Required Vendor Ethics
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

title

DT-P-0003A-24                     

AMENDMENT TO RESOLUTION DT-P-0003-24
ISSUED TO
ALFRED BENESCH & COMPANY
PROFESSIONAL CONSTRUCTION ENGINEERING SERVICES
GENEVA ROAD BRIDGE OVER THE WEST BRANCH DUPAGE RIVER
SECTION 18-00206-10-BR
(CONTRACT INCREASE $138,568.00; +16.12%)

 

resolution

WHEREAS, the DuPage County Board has heretofore approved and adopted Resolution DT-P-0003-24 on January 23, 2024; and

WHEREAS, a contract was awarded to Alfred Benesch & Company to provide Professional Construction Engineering Services for improvements at Geneva Road bridge over the West Branch of the DuPage River, Section 18-00206-10-BR (hereinafter PROJECT); and

WHEREAS, the current cost of said contract to the County of DuPage, by and through the Division of Transportation, is $859,364.00; and

WHEREAS, unforeseen conflicts with utilities arose during construction and additional extensive utility coordination were required; and

WHEREAS, increased funding is necessary to pay for the additional unanticipated work on the PROJECT; and

WHEREAS, the Transportation Committee recommends a change order to increase the contract in the amount of $138,568.00.

NOW, THEREFORE, BE IT RESOLVED that the DuPage County Board adopt this Amendment to Resolution DT-P-0003-24, issued to Alfred Benesch & Company, to increase the funding in the amount of $138,568.00, resulting in an amended contract total amount of $997,932.00, an increase of 16.12%.

end

 

Enacted and approved this 23rd day of September, 2025 at Wheaton, Illinois.

 

 