DT-P-0112A-22
AMENDMENT TO RESOLUTION DT-P-0112-22
ISSUED TO STV INCORPORATED
PHASE III CONSTRUCTION ENGINEERING SERVICES
FOR IMPROVEMENTS ALONG CH 31/87TH STREET SECTION 13-00253-01-CH
(CONTRACT INCREASE OF $248,037.81; + 36.70%)
resolution
WHEREAS, the DuPage County Board heretofore adopted Resolutions DT-P-0122-22 on April 12, 2022, which approved a Professional Services Agreement between the County of DuPage (hereinafter "COUNTY") and STV Incorporated for Professional Phase III Construction Engineering Services for improvements to CH 31/87th Street, Section 13-00253-01-CH; and
WHEREAS, the current cost of the PROJECT to the County, by and through the Division of Transportation, is $675,937.50; and
WHEREAS, as a result of various utility relocation delays, the original construction date of mid-2023 could not be adhered to, leading to an extended completion beyond mid-2023. Consequently, additional construction engineering services are required to provide continuous construction oversight post-mid-2023; and
WHEREAS, the Transportation Committee recommends a change order to increase the contract in the amount of $248,037.81 and extend the contract to October 31, 2025.
NOW, THEREFORE, BE IT RESOLVED that the DuPage County Board adopt this Amendment to Resolution DT-P-0112-22, issued to STV Incorporated, to increase the funding in the amount of $248,037.81, resulting in an amended contract total amount of $923,975.31, an increase of 36.70%; and
BE IT FURTHER RESOLVED that the County Clerk transmit a copy of this amending Resolution and any associated Illinois Department of Transportation BLR forms appropriating the necessary motor fuel tax (bond) funds to pay for the improvement to the State of Illinois Department of Transportation, by and through the Division of Transportation; and
BE IT FURTHER RESOLVED that an original copy of this Resolution and Agreement be transmitted to STV Incorporated, 200 West Monroe St...