File #: 24-2135    Version: 1
Type: Transportation Change Order with Resolution Status: Adopted
File created: 8/6/2024 In control: Transportation Committee
On agenda: 8/20/2024 Final action: 8/27/2024
Title: DT-P-0103A-23 AMENDMENT TO LOCAL PUBLIC AGENCY'S ENGINEERING SERVICES AGREEMENT, DT-P-0103-23, SUPPLEMENT #1, BETWEEN THE COUNTY OF DU PAGE AND CHRISTOPHER B. BURKE ENGINEERING, LTD. PROFESSIONAL PRELIMINARY ENGINEERING SERVICES FOR EAST BRANCH DUPAGE RIVER TRAIL (EBDRT) FROM BUTTERFIELD ROAD (IL 56) TO ILLINOIS PRAIRIE PATH (IPP) SECTION 23-00002-08-BT (TO INCREASE PRELIMINARY ENGINEERING COST $126,429.00 +8.43%)
Attachments: 1. CBBEL Change Order, 2. CBBEL Decision Memo, 3. Supporting Documents, 4. CBBEL Vendor Ethics, 5. MS Group Vendor Ethics, 6. Handout
title
DT-P-0103A-23

AMENDMENT TO LOCAL PUBLIC AGENCY'S
ENGINEERING SERVICES AGREEMENT,
DT-P-0103-23, SUPPLEMENT #1,
BETWEEN THE COUNTY OF DU PAGE
AND CHRISTOPHER B. BURKE ENGINEERING, LTD.
PROFESSIONAL PRELIMINARY ENGINEERING SERVICES
FOR EAST BRANCH DUPAGE RIVER TRAIL (EBDRT)
FROM BUTTERFIELD ROAD (IL 56) TO ILLINOIS PRAIRIE PATH (IPP)
SECTION 23-00002-08-BT
(TO INCREASE PRELIMINARY ENGINEERING COST $126,429.00 +8.43%)

resolution
WHEREAS, the DuPage County Board heretofore adopted Resolution DT-P-103-23 on November 14, 2023 which approved a Professional Services Agreement between the County of DuPage (hereinafter "COUNTY") and Christopher B. Burke Engineering, Ltd. (hereinafter "CONSULTANT") for Professional Preliminary Engineering Services ("AGREEMENT") for a multi-use path along East Branch DuPage River from Butterfield Road (IL 56) to the Illinois Prairie Path (IPP), Section # 23-00002-08-BT (hereinafter referred to as "PROJECT"); and
WHEREAS, the current cost of the PROJECT to the County of DuPage, by and through the Division of Transportation, is $1,500,000.00 (COUNTY to be reimbursed $1,200,000.00); and
WHEREAS, after the coordination with CONSULTANT, additional scope items outside the original Phase I AGREEMENT have been identified by the County as necessary, including the addition of assistance with stakeholder outreach for the PROJECT causing an increase in cost due to the additional scope of work; and
WHEREAS, the Transportation Committee recommends a change order to increase the COUNTY's share of the preliminary engineering contract in the amount of $126,429.00 with an amendment to the AGREEMENT ("AMENDMENT").
NOW, THEREFORE, BE IT RESOLVED that the DuPage County Board adopts this AMENDMENT to Resolution DT-P-0103-23, issued to Christopher B. Burke Engineering, Ltd., to increase the COUNTY's funding in the amount of $126,429.00, resulting in an amended contract total amount of $1,626,429.00 an increase of 8.43%; a...

Click here for full text