File #: PW-P-0021-25    Version: 1
Type: Public Works Requisition $30,000 and Over Status: Adopted
File created: 7/22/2025 In control: Public Works Committee
On agenda: 8/5/2025 Final action: 8/12/2025
Title: AWARDING RESOLUTION ISSUED TO COMMERCIAL MECHANICAL, INC. FOR BOILER REPLACEMENT AND RELATED CONSTRUCTION FOR PUBLIC WORKS (CONTRACT TOTAL AMOUNT $1,086,800)
Attachments: 1. CMI PRCC, 2. BID Tabulation 25-090-PW, 3. Required Forms CMI_Redacted, 4. CMI Vendor Ethics

title

AWARDING RESOLUTION ISSUED TO

COMMERCIAL MECHANICAL, INC.

FOR BOILER REPLACEMENT AND RELATED CONSTRUCTION

FOR PUBLIC WORKS

(CONTRACT TOTAL AMOUNT $1,086,800)

 

resolution

                     WHEREAS, proposals have been taken and evaluated in accordance with County Board policy; and

 

WHEREAS, the Public Works Committee recommends County Board approval for the issuance of a contract to Commercial Mechanical, Inc., for boiler replacement and related construction, for the period of August 12, 2025 through November 30, 2026, for Public Works.

 

NOW, THEREFORE BE IT RESOLVED, that said contract is for boiler replacement and related construction, for the period of August 12, 2025 through November 30, 2026, for Public Works, per Bid 25-090-PW, be, and it is hereby approved for the issuance of a contract purchase order by the Procurement Division to Commercial Mechanical, Inc., 50 N. First Street, Dunlap, Illinois 61525, for a contract total amount of $1,086,800.

end

 

Enacted and approved this 12th day of August, 2025 at Wheaton, Illinois.

 

 

 

________________________________

DEBORAH A. CONROY, CHAIR

DU PAGE COUNTY BOARD

 

 

Attest: ___________________________________

JEAN KACZMAREK, COUNTY CLERK