File #: 23-2251    Version: 1
Type: Change Order Status: Adopted
File created: 6/28/2023 In control: Transportation Committee
On agenda: 7/11/2023 Final action: 7/18/2023
Title: DT-R-0242B-21 AMENDMENT TO RESOLUTION DT-R-0242A-21 ISSUED TO H&H ELECTRIC COMPANY MAST ARM REPLACEMENT AND TRAFFIC SIGNAL MODIFICATIONS AT VARIOUS LOCATIONS WITHIN DU PAGE COUNTY SECTION 21-TSMAR-01-GM (TO INCREASE CONTRACT BY: $1,098.82; +0.18%, A CUMMULATIVE INCREASE OF $12,598.82, 2.06%)
Attachments: 1. H & H Change Order, 2. H & H Supporting Data for Amendment, 3. H & H Vendor Ethics

title

DT-R-0242B-21

AMENDMENT TO RESOLUTION DT-R-0242A-21

ISSUED TO H&H ELECTRIC COMPANY

MAST ARM REPLACEMENT AND TRAFFIC SIGNAL MODIFICATIONS

AT VARIOUS LOCATIONS WITHIN DU PAGE COUNTY

SECTION 21-TSMAR-01-GM (TO INCREASE CONTRACT BY: $1,098.82; +0.18%,

A CUMMULATIVE INCREASE OF $12,598.82, 2.06%)

 

resolution

WHEREAS, the DuPage County Board heretofore adopted Resolution DT-R-0242A-21 on November 8, 2022 and DT-R-0242-21 on April 27, 2021 which awarded a contract to H & H Electric Company for mast arm replacement and traffic signal modification at various intersections within DuPage County, Section 21-TSMAR-02-GM; and

WHEREAS, the current cost of the PROJECT to the County of DuPage, by and through the Division of Transportation, is $623,603.55; and

WHEREAS, additional exploration and excavation work was required due to an unknown and unmarked utility facility; and

WHEREAS, the circumstances that necessitate the change in costs were not reasonably foreseeable at the time the contract was signed; and

WHEREAS, additional funds are necessary for H & H Electric Company to complete the changes needed in the scope of services; and

WHEREAS, the Transportation Committee recommends a change order to increase the contract in the amount of $1,098.82 in order to complete the changes needed.

 

NOW, THEREFORE, BE IT RESOLVED that the DuPage County Board adopt this Amendment to Resolution DT-R-0242A-21, issued to H & H Electric Company to increase the funding in the amount of $1,098.82, resulting in an amended contract total amount of $624,702.37, an increase of 0.18%, and a cumulative increase of $12,598.82, +2.06%.

end

 

Enacted and approved this 18th day of July, 2023 at Wheaton, Illinois.

 

 

 

________________________________

DEBORAH A. CONROY, CHAIR

DU PAGE COUNTY BOARD

 

 

Attest: ___________________________________

JEAN KACZMAREK, COUNTY CLERK