DT-R-0058A-23

AMENDMENT TO RESOLUTION DT-R-0058-23
ISSUED TO MANEVAL CONSTRUCTION COMPANY, INC.
TO PROVIDE PARKING LOT IMPROVEMENTS
FOR THE DUPAGE COUNTY FAIRGROUNDS
(CONTRACT INCREASE $75,000.00; +21.25%,

NO COUNTY COST-100% GRANT FUNDED)

 

resolution

WHEREAS, the DuPage County Board heretofore adopted Resolution DT-R-0058-23 on April 11th, 2023; and

WHEREAS, a contract was awarded by County Board Resolution DT-R-0058-23 to Maneval Construction Company, Inc. to provide parking lot improvements for the DuPage County Fairgrounds; and

WHEREAS, the Fairgrounds and County staff identified additional areas eligible for improvement which were not in the original contract; and

WHEREAS, the circumstances that necessitate the change in costs were not reasonably foreseeable at the time the contract was signed; and

WHEREAS, there is sufficient unobligated funds remaining under the grant award to pay for these additional improvement areas; and

WHEREAS, an adjustment in funding is in the best interest of the County and is authorized by law.

NOW, THEREFORE, BE IT RESOLVED that Resolution DT-R-0058-23 is hereby amended to reflect a cost of $428,014.45 instead of and in place of a cost of $353,014.45, an increase of $75,000.00, +21.25%.

end

Enacted and approved this 25th day of April, 2023 at Wheaton, Illinois.

 

 

________________________________

DEBORAH A. CONROY, CHAIR

DU PAGE COUNTY BOARD

 

 

Attest: ___________________________________

JEAN KACZMAREK, COUNTY CLERK