title
DT-R-0006A-26
AMENDMENT TO RESOLUTION DT-R-0003A-26
ISSUED TO K-FIVE CONSTRUCTION CORPORATION
2026 ROADWAY RESURFACING (NORTH) PROGRAM
SECTION 26-00330-00-RS
(CONTRACT INCREASE $159,570.96; +3.14%)
resolution
WHEREAS, a contract was awarded by County Board Resolution DT-R-0006-26 to K-Five Construction Corporation for the 2026 Roadway resurfacing (North) Program, Section 26-00330-00-RS; and
WHEREAS, to promote proper drainage of the County highways resurfaced under this contract it was necessary to replace additional curb and gutter that was found to be more deteriorated than had been previously observed at the time the contract was prepared; and
WHEREAS, additional work was required to repair the base of St. Charles Road due to unforeseen site conditions; and
WHEREAS, changes to the contract plans, pay items and/or contract quantities were necessary due to field conditions, as listed on the attached “Supporting Data for Amendment”; and
WHEREAS, County staff independently reviewed the field conditions and confirmed the need for the extra work.
WHEREAS, the circumstances that necessitate the change in costs were not reasonably foreseeable at the time the contract was signed; and
WHEREAS, an adjustment in funding is in the best interest of the County and is authorized by law.
NOW, THEREFORE, BE IT RESOLVED that Resolution DT-R-00006-26 is hereby amended to reflect a cost of $5,078,562.22 instead of and in place of a cost of $4,918,991.26, an increase of $159,570.96, +3.14%.
end
Enacted and approved this 24th day of November, 2026 at Wheaton, Illinois.
________________________________
DEBORAH A. CONROY, CHAIR
DU PAGE COUNTY BOARD
Attest: ___________________________________
JEAN KACZMAREK, COUNTY CLERK