19.A.
Recommendation for the approval of a contract to Wight Construction Services, Inc., to
provide Professional Construction Manager as Advisor Services, for the JTK
Administration Building HVAC Replacement project, for Facilities Management, for the
period August 13, 2024 through December 31, 2026, for a total contract amount not to
exceed $1,588,928. Professional Services (Architects, Engineers and Land Surveyors)
vetted through a qualification-based selection process in compliance with the Illinois
Local Government Professional Services Selection Act, 50 ILCS 510/.01 et seq.
(PARTIAL ARPA ITEM)
19.B.
19.C.
19.D.
Recommendation for the approval of a contract to Air Filter Solutions LLC, to furnish
and deliver air filters, as needed, for County facilities, for Facilities Management, for the
period of September 27, 2024 through September 26, 2025, for a total contract amount
not to exceed $138,100, per renewal option under bid award #23-053-FM. ($130,000 for
Facilities Management, $4,000 for Animal Services, $1,100 for Division of
Transportation, and $3,000 for Health Department). First of three options to renew.
Recommendation for the approval of a contract to Mohr Oil Company, to furnish and
deliver non-highway use #1 and #2 red dyed diesel fuel for the Public Works emergency
generators at Woodridge Greene Valley Wastewater Treatment Plant, Knollwood
Wastewater Treatment Plant and Nordic Wastewater Treatment Plant, for the period of
August 13, 2024 to August 12, 2026, for a total contract amount not to exceed $100,000;
per lowest responsible bid #24-074-FM.
Recommendation for the approval of a contract to LAI Ltd., for the purchase of
DeZurick, Inc., APCO, Inc., Hilton Brand, and Red Valve representation repair parts, as
well as Rotork valve actuators and repair parts, for the Woodridge Greene Valley
Wastewater Treatment Facility, Knollwood Wastewater Treatment Facility, and Nordic
Wastewater Treatment Facility, for Public Works, for the period of August 13, 2024 to
August 12, 2028, for a total contract amount not to exceed $200,000. Per 55 ILCS
5/5-1022(c) not suitable for competitive bids. (Sole Source – Direct replacement of parts
and service for valves and actuators.)
19.E.
Acceptance of the Substantive and Technical changes to Chapter 36 of the DuPage
County Water Supply, Distribution and Wastewater Treatment Ordinance.
20.
STORMWATER - ZAY
Committee Update
20.A.
Resolution approving an agreement between the County of DuPage, Illinois and St.
Joseph Creek Condominium Association for the St. Joseph Creek Condominium Flood
Mitigation Project.