6.D.
Recommendation for the approval of a contract to Ciorba Group, Inc., for Professional
Phase I Preliminary Engineering Services for improvements along CH 4/Bloomingdale
Road Bridge Improvements over Chicago Central & Pacific Railroad, Section
22-00184-12-BR, for a contract total not to exceed $308,511. Professional Services
(Architects, Engineers and Land Surveyors) vetted through a qualification-based selection
process in compliance with the Illinois Local Government Professional Services
Selection Act, 50 ILCS 510/0.01 et seq.
7.
CHANGE ORDERS
7.A.
7.B.
7.C.
7.D.
7.E.
7.F.
7.G.
7.H.
BLA, Inc. PO # 5752-1-SERV, Extend contract to October 31, 2026. No change in
contact encumbrance.
HR Green, Inc. PO # 5638-1-SERV, Extend contract to October 31, 2026. No change in
contract encumbrance.
HW Lochner, Inc. PO # 3595-1-SERV, Extend contract to October 31, 2026. No change
in contract encumbrance.
HW Lochner, Inc. PO #5277-1-SERV, Extend contract to October 31, 2026. No change
in contract encumbrance.
Knight E/A, Inc. PO # 5805-1-SERV, Extend contract to May 31, 2027. No change in
contract encumbrance.
Rush Truck Centers of Illinois, Inc. PO # 5896-1-SERV, Extend contract to November
30, 2026. No change in contract encumbrance.
STV, Incorporated, PO # 5751-1-SERV, Extend contract to October 31, 2026. No change
in contract encumbrance.
DT-P-0003B-24 - Amendment to DT-P-0003A-24, which increased the contract amount
issued to Alfred Benesch by $138,568; due to a scrivener’s error the increase should have
read $138,658, making the new contract amount $1,001,997, an increase of 16.06%.