7.D.1.
Facilities Management – Transfer of funds from account number 1000-1180-53828
(Contingencies) in the amount of $592,000 to 1000-1100-53210 (Electricity) to cover the
cost of electricity for Facilities Management in the FY25 fiscal year.
7.D.2.
7.D.3.
Renewal of the Steeple Run Water Tower Lease Agreement with Verizon Wireless.
Recommendation for the approval of a contract to Helm Mechanical, to furnish, deliver,
and install a domestic hot water storage tank for the Jail, for Facilities Management, for
the period of December 10, 2025 through December 9, 2026 for a contract total amount
not to exceed $107,558; per lowest responsible bid #25-123-FM.
7.D.4.
Recommendation for the approval of a contract purchase order to HD Supply, Inc. d/b/a
HD Supply Facilities Maintenance, LTD., for maintenance, repair, operating and cleaning
supplies, for various Public Works Facilities, for the period of December 9, 2025 through
June 30, 2027, for a total contract amount not to exceed $45,000. Contract pursuant to the
Intergovernmental Cooperation Act (Omnia Contract #25-JH-011).
E.
Stormwater - Zay
7.E.1.
Recommendation for the approval of a contract to Christopher B. Burke Engineering
LTD, for Professional Engineering Services for the development of the Sawmill Creek
Watershed Plan, for the period of December 9, 2025 through June 30, 2027, for a contract
total not to exceed $98,500. Other Professional Services (Architects, Engineers and Land
Surveyors) vetted through a qualification-based selection process in compliance with the
Local Government Professional Services Selection Act, 50 ILCS 510/0.01 et seq.
7.E.2.
Recommendation for the approval of a contract issued to Hampton, Lenzini and Renwick,
Inc., for professional engineering/GIS Floodplain Mapping services, for Stormwater
Management, for the period of December 9, 2025 through November 30, 2026, for a
contract total not to exceed $75,000. Professional Services (Architects, Engineers and
Land Surveyors) vetted through a qualification based selection process in compliance
with the Illinois Local Government Professional Services Selection Act, 50 ILCS 510/et
seq.
7.E.3.
Recommendation for the approval of a contract issued to Gewalt Hamilton Associates,
Inc., for professional engineering and land surveying services, for Stormwater
Management, for the period of December 9, 2025 through November 30, 2026, for a
contract total not to exceed $65,000. Professional Services (Architects, Engineers and
Land Surveyors) vetted through a qualification based selection process in compliance
with the Illinois Local Government Professional Services Selection Act, 50 ILCS 510/et
seq.