8.B.
Recommendation for the approval of a contract to Earthwerks Land Improvement and
Development Corporation, for construction of stormwater detention and Best
Management Practices (BMP’s) projects at the east campus detention basin, for Facilities
Management, for numerous building construction projects, for the period May 23, 2023,
through December 15, 2025 for a total lump sum amount of $2,793,517 which includes
$364,371 (15%) owner contingency, per lowest responsible bid 22-102-SWM.
(PARTIAL ARPA ITEM)
9.
PROFESSIONAL SERVICES AGREEMENT
9.A.
Recommendation for the approval of an Agreement between the County of DuPage,
Illinois, and V3 Companies, Ltd., to provide Phase III Professional Stormwater
Engineering Services and engineering design for campus projects, for Facilities
Management, for the period May 23, 2023 through December 15, 2025, for a total
contract amount not to exceed $241,095. Professional Services (Architects, Engineers
and Land Surveyors) vetted through a qualification-based selection process in compliance
with the Illinois Local Government Professional Services Selection Act, 50 ILCS 510/ et
seq.
10.
11.
12.
SOLE SOURCE
10.A.
Recommendation for the approval of a contract to RapidView, LLC, for parts and labor
to repair the IBAK sewer televising camera, for Public Works, for the period of May 23,
2023 to May 31, 2027, for a contract total amount not to exceed $60,000; per 55 ILCS
5/5-1022 "Competitive Bids" (c) not suitable for competitive bids - Sole Source.
ACTION ITEMS
11.A.
Recommendation for the approval of an Easement Agreement between the County of
DuPage and the Forest Preserve District of DuPage County providing for the operation
and maintenance of existing sanitary interceptors within portions of the Waterfall Glen
Forest Preserve. (No additional cost to the County)
PRESENTATIONS
12.A. County Campus EV Charging Stations
12.B. DuPage County Historical Museum & DuPage County Heritage Gallery
13.
14.
15.
OLD BUSINESS
NEW BUSINESS