specification of the EV Charging Station and Chief Administrative Officer Nick
Kottmeyer and Director of Facilities Management Tim Harbaugh responded.
APPROVED AND SENT TO FINANCE
Michael Childress
RESULT:
MOVER:
Paula Garcia
SECONDER:
8.
BID AWARD
8.A.
Recommendation for the approval of a contract to Nedrow Painting, Inc., d/b/a Nedrow
Decorating, Inc., to provide painting of roof top cooling tower structure at the Power
Plant, for Facilities Management, for the period of September 24, 2025 through
September 23, 2026, for a total contract amount not to exceed $53,475; per lowest
responsible bid #25-096-FM.
APPROVED AND SENT TO FINANCE
Michael Childress
RESULT:
MOVER:
Paula Garcia
SECONDER:
9.
BID RENEWAL
9.A.
Recommendation for the approval of a contract to Builders Chicago Corporation, to
provide preventive maintenance, service and repairs for overhead doors, roll-up shutters,
gate operators, dock levelers and revolving doors, as needed, for County facilities, for
Facilities Management, for the period of November 1, 2025 through October 31, 2027,
for a total contract amount not to exceed $214,300; per renewal option under bid award
#23-091-FM. First and final option to renew. ($143,300 - Facilities Management,
$30,000 - Division of Transportation, and $41,000 - Public Works)
APPROVED AND SENT TO FINANCE
Michael Childress
RESULT:
MOVER:
Paula Garcia
SECONDER:
9.B.
Amendment to FM-P-0041-25 issued to Builders Chicago Corporation, to provide
preventive maintenance, service, and repairs for overhead doors, roll-up shutters, gate
operators, dock levelers and revolving doors, as needed for County facilities, for
Facilities Management, increasing the total contract price by 2%.
APPROVED AND SENT TO FINANCE
Michael Childress
RESULT:
MOVER:
Paula Garcia
SECONDER: