9.B.
V3 Companies Ltd. - PO 8034-0001-SERV - Change Order to extend the contract for
On-Call Professional Engineering Services, from November 30, 2026 to November 30,
2027, no change to contract amount.
9.C.
9.D.
Martam Construction - PO 6228-0001-SERV - Change Order to extend the contract from
November 30, 2026 to November 30, 2027, no change to contract amount.
First amendment to Resolution SM-R-0005-26, between Milton Township Highway
Department and DuPage County, for the National Street Drainage Improvement Project,
to extend the Intergovernmental Agreement end date to November 30, 2027.
9.E.
Recommendation for the approval of a contract with V3 Construction Group, LTD, for
the Kress Creek Upstream Weir Repair Project, for Stormwater Management, for the
period of October 13, 2026 through November 30, 2030, for a contract total amount not
to exceed $188,658; per bid #26-081-SWM.
10.
INFORMATIONAL
10.A.
Recommendation for the approval of a contract to Sutton Ford, Inc., for a F-550 4X2
Regular Chassis Cab with a Monroe crane service body attachment, for Public Works, for
the period of October 13, 2026 to June 30, 2027, for a total contract amount not to exceed
$193,008. Contract pursuant to the Governmental Joint Purchasing Act, 30 ILCS 525/2
(Suburban Purchasing Cooperative #227).
11.
12.
13.
OLD BUSINESS
NEW BUSINESS